Question: Activity Normal Time Crash Time Normal Cost Total Cost Immediate Predecessors A 6 5 800 1000 B 7 6 200 350 C 5 3 600

Activity Normal Time Crash Time Normal Cost Total Cost Immediate Predecessors

A 6 5 800 1000

B 7 6 200 350

C 5 3 600 750

D 5 3 900 1250 A,B

E 8 5 1100 1850 C

The minimum cost of crashing the following project at Sawaya Robotics by 4 days is_____?