Question: Activity Normal Time Crash Time Normal $ Crash $ D . 4 2 1,000 2,000 B 10 00 8 2,000 4,000 14 11 1,000 2,800

Activity Normal Time Crash Time Normal $ Crash $

Activity Normal Time Crash Time Normal $ Crash $ D . 4 2 1,000 2,000 B 10 00 8 2,000 4,000 14 11 1,000 2,800 D 15 12 1,000 10,000 E 12 11 2,000 4,000 F 1 1 500 500 G 8 4 1,500 7,500 H 7 6 800 1,600 The Project has three feasible paths: -C-D-F-H B-D-F-H B-E-G-H The Project manager wants to reduce the project completion by three weeks. QUESTION: What is the new (or Crashed) project duration in Weeks