Question: ACTIVITY NORMAL TIME ( DAYS ) CRASH TIME ( DAYS ) NORMAL COST CRASH COST IMMEDIATE PREDECESSOR ( S ) Design ( A ) 6

ACTIVITY NORMAL TIME (DAYS) CRASH TIME (DAYS) NORMAL COST CRASH COST IMMEDIATE PREDECESSOR(S)
Design (A)659001,000-
Wiring (B)86300400-
Chip install (C)43500600-
Software (D)539001,200 A, B
Testing (E)851,0001,600 C