Question: For the following project: Activity Normal Time ( Weeks ) Crash Time ( Weeks ) Normal Cost Crash Cost Immediate Predecessor A 4 3 2

For the following project:
Activity
Normal Time
(Weeks)
Crash Time
(Weeks)
Normal Cost
Crash Cost
Immediate
Predecessor
A
4
3
2,000
2,100
-
B
2
1
2,200
2,800
-
C
3
3
500
500
-
D
8
7
2,300
2,500
A
E
6
3
900
1,200
B
F
3
2
3,000
4,200
C
G
4
2
1,400
2,000
D, E
How much will the cost increase if it is crashed maximum?
1000
1350
1200
900
1100