Question: Activity Normal Time Normal Cost Crash Time Crash Cost A 5 $300 5 $300 B 8 $250 5 $400 C 2 $100 2 $100 D
Activity Normal Time Normal Cost Crash Time Crash Cost
A 5 $300 5 $300
B 8 $250 5 $400
C 2 $100 2 $100
D 6 $300 3 $600
E 3 $150 2 $300
F 4 $275 3 $300
G 9 $700 8 $900
Questions
- Perform the activities crashing until it can no longer be crashed. What is the total cost?
- If there is a bonus of $125 per day for finishing early, what activities would be crashed, and how fast would the project be completed?