Question: For the following test marketing project at week 6: a. Ignore the far right % Complete column and using the 5050 percent completion rule for
For the following test marketing project at week 6:
a. Ignore the far right % Complete column and using the 5050 percent completion rule for PV and EV, calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC.
b. Repeat the calculations in a, but now using the % Complete column. Assume that the PV values are based on time proportionality but the % Complete values for EV are from the workers actually doing thetasks.
a. Ignore the far right % Complete column and using the 5050 percent completion rule for PV and EV, calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC.
b. Repeat the calculations in a, but now using the % Complete column. Assume that the PV values are based on time proportionality but the % Complete values for EV are from the workers actually doing thetasks.
.png)
Activity Predecessors Duration Budget, S Actual Cost, $ % Complete (weeks) a: Build items b: Supply stores c: Create ad progranm d: Schedule ads e: Check sale results 300 200 250 600 400 400 180 300 400 200 100 100 100 20 20 b, c
Step by Step Solution
★★★★★
3.42 Rating (165 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
a Figure 108a shows the solution table for problem 8 ETC BAC EV CPI EAC ETC AC TV SV PV Wks The week... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
Document Format (1 attachment)
84-B-M-L-P-M (283).docx
120 KBs Word File