Question: Activity Optimistic Most Likely Pessimistic A 1012 B 8 10 C 6 7 D 8 11 E 17 28 =coco mo 00 End The probability

Activity Optimistic Most Likely Pessimistic A

Activity Optimistic Most Likely Pessimistic A 1012 B 8 10 C 6 7 D 8 11 E 17 28 =coco mo 00 End The probability that the project will finish in 25 days is: 96% 50% 76% 24%