Question: A short project is defined by activities with three time estimates ( in days ) as shown in the table. Activity Optimistic Most Likely Pessimistic

A short project is defined by activities with three time estimates (in days) as shown in the table.
Activity
Optimistic
Most Likely
Pessimistic
Predecessor
A
4
6
8
B
5
9
13
C
10
12
15
A, B
D
9
12
16
B
E
6
9
15
D
F
10
13
18
C
What is the standard deviation of the project's completion time?