Question: Activity Optimistic Most Probable Pessimistic A 2 5 6 B 1 3 7 C 7 9 13 D 4 10 12 E 3 4 7
| Activity | Optimistic | Most Probable | Pessimistic |
| A | 2 | 5 | 6 |
| B | 1 | 3 | 7 |
| C | 7 | 9 | 13 |
| D | 4 | 10 | 12 |
| E | 3 | 4 | 7 |
| F | 6 | 8 | 14 |
| G | 3 | 6 | 10 |
|
|
|
|
|
|
|
|
|
|
Calculate the probability that the project will be completed in 21 units of time or less based on the following additional information Expected completion time equals 24.17 and the critical path equals C-F-G. (Show detail work)
Step by Step Solution
There are 3 Steps involved in it