Question: Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A -- 2 5 8 B -- 2 3
Consider a project that has been modeled as follows:
Activity Immediate Predecessors Optimistic Most Probable Pessimistic
A -- 2 5 8
B -- 2 3 7
C -- 5 7 9
D A 7 12 14
E A 3 4 5
F A,B 6 9 12
G C 4 6 8
H C 4 6 8
I E,F,G 5 7 12
J H 12 13 14
K D ,I,J 2 3 4
What is the Critical Path?