Question: Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A -- 2 5 8 B -- 2 3

Consider a project that has been modeled as follows:

Activity Immediate Predecessors Optimistic Most Probable Pessimistic

A -- 2 5 8

B -- 2 3 7

C -- 5 7 9

D A 7 12 14

E A 3 4 5

F A,B 6 9 12

G C 4 6 8

H C 4 6 8

I E,F,G 5 7 12

J H 12 13 14

K D ,I,J 2 3 4

What is the Critical Path?