Question: Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A 2 5 8 B 2 3 7 C

Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A 2 5 8 B 2 3 7 C UT 7 D A 7 12 14 E A 3 4 5 F A, B 6 12 G C I 4 6 8 H C 4 6 8 E,F.G UT N 12 H 12 13 14 K D,I,J 2 4 How many days should I give myself to ensure a 95% probability of completing? O 30.73 O 33.85 28.56 32.20