Question: Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A 2 5 8 B 2 3 7 C

 Consider a project that has been modeled as follows: Activity Immediate

Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A 2 5 8 B 2 3 7 C UT 7 D A 7 12 14 E A 3 4 5 F A, B 6 12 G C I 4 6 8 H C 4 6 8 E,F.G UT N 12 H 12 13 14 K D,I,J 2 4 How many days should I give myself to ensure a 95% probability of completing? O 30.73 O 33.85 28.56 32.20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!