Question: Activity Optimistic Pessimistic Preceding Activity Most Likely 2 A 4 12 B 10 12 26 C 8 9 10 D A 10 15 20 E

Activity Optimistic Pessimistic Preceding Activity Most Likely 2 A 4 12 B 10 12 26 C 8 9 10 D A 10 15 20 E A 7 7.5 11 F B.C 9 9 9 G D 3 3.5 7 H E,F,G 5 5 5 (a) Find expected project duration and determine critical path. (b) If a 30 week deadline is imposed, what is the probability that the project is completed within time limits? (c) If there is 99% probability for project to be completed, how many weeks before should project start