Question: Activity OPTIMISTIC TIMES (days). MOST LIKELY tm Start Finish Node Node PESSIMISTIC 1 2 34 13 27 42 50 2 3 E 458 66 |

Activity OPTIMISTIC TIMES (days). MOST LIKELY tm

Activity OPTIMISTIC TIMES (days). MOST LIKELY tm Start Finish Node Node PESSIMISTIC 1 2 34 13 27 42 50 2 3 E 458 66 | Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity A.........te = 37 Standard Deviation = 6 Activity B.........te = Standard Deviation Activity C.........te = Standard Deviation = Activity D.........te = Standard Deviation = Activity E.........te = Standard Deviation = 6 Path 1-2-5 Mean Time = Standard Deviation =10 Path 1-3-4-5 Mean Time = Standard Deviation =