Question: Activity P M O Expected Activity Duration (Beta Distribution) Beta Activity Standard Deviation Range of Estimate Start End A 45 25 15 B 89 61

Activity P M O Expected Activity Duration (Beta Distribution) Beta Activity Standard Deviation Range of Estimate
Start End
A 45 25 15
B 89 61 40
C 47 43 38

Using Beta Distribution, which activity is the riskiest?

a.

Activity B

b.

Both Activity A and B

c.

Activity C

d.

Activity A