Question: Activity P M O Expected Activity Duration (Beta Distribution) Beta Activity Standard Deviation Range of Estimate Start End A 45 25 18 B 85 61
| Activity | P | M | O | Expected Activity Duration (Beta Distribution) | Beta Activity Standard Deviation | Range of Estimate | |
| Start | End | ||||||
| A | 45 | 25 | 18 | ||||
| B | 85 | 61 | 40 | ||||
| C | 47 | 43 | 35 | ||||
THREE-POINT ESTIMATING:
Using the Beta Distribution, what is the standard deviation for Activity B?
a.
54.000
b.
61.500
c.
6.500
d.
7.500
In the three-point estimating- beta distribution problem, what is the least range of duration for Activity A?
a.
27.169
b.
22.662
c.
22.667
d.
27.167
In the three-point estimating- beta distribution problem, what is the highest range of duration for Activity C?
a.
44.332
b.
45.333
c.
44.333
d.
40.333
In the three-point estimating- beta distribution problem, which activity is the highest risk?
a.
None of the choices
b.
B
c.
A
d.
C