Question: Activity P M O Expected Activity Duration (Beta Distribution) Beta Activity Standard Deviation Range of Estimate Start End A 45 25 18 B 85 61

Activity P M O Expected Activity Duration (Beta Distribution) Beta Activity Standard Deviation Range of Estimate
Start End
A 45 25 18
B 85 61 40
C 47 43 35

THREE-POINT ESTIMATING:

Using the Beta Distribution, what is the standard deviation for Activity B?

a.

54.000

b.

61.500

c.

6.500

d.

7.500

In the three-point estimating- beta distribution problem, what is the least range of duration for Activity A?

a.

27.169

b.

22.662

c.

22.667

d.

27.167

In the three-point estimating- beta distribution problem, what is the highest range of duration for Activity C?

a.

44.332

b.

45.333

c.

44.333

d.

40.333

In the three-point estimating- beta distribution problem, which activity is the highest risk?

a.

None of the choices

b.

B

c.

A

d.

C

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!