Question: Activity P M O Expected Activity Duration ( Beta Distribution ) Beta Activity Standard Deviation Range of Estimate Start End J 3 5 2 5

Activity P M O Expected Activity Duration (Beta Distribution) Beta Activity Standard Deviation Range of Estimate
Start End
J
35
2516
K
77
6045
L
55
4438
Using the Beta Distribution,calculate the Expected Activity Distribution (EAD), Standard Deviation and Range of Estimate. Calculate to three decimal places. What is the end range for Activity J?
a.
28.667
b.
25.167
c.
28.334
d.
28.330