Question: Activity Pessimistic * Preceding Optimistic Most activity Likely 8 3 A 7 A 6 2 8 B, C 4 1 B, D 6 4 E,

Activity Pessimistic * Preceding Optimistic Most

Activity Pessimistic * Preceding Optimistic Most activity Likely 8 3 A 7 A 6 2 8 B, C 4 1 B, D 6 4 E, F 3 2 Project's budget per day $800 A B D E F G * 600 300 500 400 350 100 550 a. Draw an AON diagram based on the activities and their relationships given in the table. (2 Marks) b. Develop a crashing schedule [ Replace the * with any value in between 3-5]