Question: Activity Precedence Duration A - 3 B - 1 C - 5 D A 1 E C 6 F E 2 G B,D.F 2 H
| Activity | Precedence | Duration |
| A | - | 3 |
| B | - | 1 |
| C | - | 5 |
| D | A | 1 |
| E | C | 6 |
| F | E | 2 |
| G | B,D.F | 2 |
| H | G | 8 |
| I | H,E | 3 |
Draw the ealiest due date network diagram and identify the critical path.