Question: Activity Precedence Duration A. ? 3 B ? 4 C. ? 5 D A,B. 6 E B,C 7 F D,E 8 G F. 9 What

Activity Precedence Duration

A. ? 3

B ? 4

C. ? 5

D A,B. 6

E B,C 7

F D,E 8

G F. 9

  1. What is the projects duration?
  2. What is the critical path?