Question: Question 1 options: Activity Precedence Duration A 3 B 4 C 3 D A,B 6 E B,C 5 F D, E 2 G F 4

Question 1 options:

Activity Precedence Duration A 3 B 4 C 3 D A,B 6 E B,C 5 F D, E 2 G F 4

What is the project's duration?

What is the critical path?

Write your answer as: A B C Type in: A (space) B (space) C