A new application development project at ACME7365 Inc. consists of the following activities:
| Activity | Predecessor | Estimated Duration (Days) |
| A | 3 | |
| B | 4 | |
| C | 4 | |
| D | A | 3 |
| E | D | 4 |
| F | E | 3 |
| G | F | 4 |
| H | F | 5 |
| I | G, H | 6 |
| J | G | 3 |
| K | H | 4 |
| L | I, K | 5 |
| M | J | 2 |
- Crash the project by 3 days and re-identify the critical path?