Question: Activity Precedence Duration Max Reducible Duration A - 7 2 B A 3 0 C B 9 3 D A 10 3 E C, D

Activity

Precedence

Duration

Max Reducible Duration

A

-

7

2

B

A

3

0

C

B

9

3

D

A

10

3

E

C, D

7

3

F

E

3

1

Without crashing, how long does it take to finish this project?