Question: Activity Precedence Duration Max Reducible Duration A - 7 2 B A 3 0 C B 9 3 D A 10 3 E C, D
| Activity | Precedence | Duration | Max Reducible Duration |
| A | - | 7 | 2 |
| B | A | 3 | 0 |
| C | B | 9 | 3 |
| D | A | 10 | 3 |
| E | C, D | 7 | 3 |
| F | E | 3 | 1 |
Without crashing, how long does it take to finish this project?