Question: Activity Precedent Crash Crashed Normal Normal S Time Cost time costs a 4 800 7 500 b a 2 350 3 200 C a

Activity Precedent Crash Crashed Normal Normal S Time Cost time costs a

Activity Precedent Crash Crashed Normal Normal S Time Cost time costs a 4 800 7 500 b a 2 350 3 200 C a 4 900 6 500 d b 1 500 3 200 1 550 2 300 (1) C 1700 Find: Crash cost per day; the activities that should be crashed to meet a project deadline of 10 days with a minimum cost; the new cost.