Question: Activity Precedes C . E F B D E F G H 1 Duration in weeks 4 5 7 12 6 6 3 4 7

Activity Precedes C . E F B D E F G H 1 Duration in weeks 4 5 7 12 6 6 3 4 7 5 Available Cost of weeks to Crash Crashing $300 2 $200 1 $500 2 $300 2 $700 1 $500 0 N/A 1 $200 1 $800 1 $200 G 1 1 end a) Draw the precedence network OPMG 2258 Page 4 Assignment 2 b) Indicate the paths to project completion, their duration, and slack. Which one is the critical path? c) For each activity, use the PERT/CPM solution technique to show the early start, early finish, last start, and late finish d) We need to reduce the project by 4 weeks - which activities do we crash? What is the total cost of crashing this project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
