Question: Activity Precedes Duration (Days) Start a, b, a d 5 d f 6 2 b e 5 e f 9 C h 4 h B.

Activity Precedes Duration (Days) Start a, b, a d
Activity Precedes Duration (Days) Start a, b, a d 5 d f 6 2 b e 5 e f 9 C h 4 h B. 6 8 end 3 end 1 Which of the following statements is not true? O a. Activity D can be delayed up to 3 delayed without impacting the timely completion of the project, Obif Activity bis delayed by up to 5 days, the project will not be delayed O c. All answers presented are true d. The latest start time for Activity dis 8 e Activity g 5 part of the critical path