Question: Activity Precedes Duration (Days) Start a, b, c a d 5 d f 6 f 8 2 b CD 5 e f 9 h 4

Activity Precedes Duration (Days) Start a, b, c a
Activity Precedes Duration (Days) Start a, b, c a d 5 d f 6 f 8 2 b CD 5 e f 9 h 4 h 8, i 6 8 end 3 end 1 What is the critical path for this project? O a.c-h- O b.b-e-f-g Oca-d-f-g O d.none of the answers presented Oe.c-h-g