Question: Activity Preceding Activities Completion Times (to, tm, tp) A - 5, 6, 7 B - 4, 5, 6 C B 3, 4, 5 D C
| Activity | Preceding Activities | Completion Times (to, tm, tp) |
|---|---|---|
| A | - | 5, 6, 7 |
| B | - | 4, 5, 6 |
| C | B | 3, 4, 5 |
| D | C | 10, 12, 14 |
| E | A, D | 5, 6, 7 |
| F | C, E | 3, 10, 11 |
| G | E | 4, 5, 6 |
| H | G, F | 5, 7, 9 |
- Find the slack time (delay time) of each of the activities, the critical and the non-critical activities.
- Find the probability of completing the project in 45 weeks.