Question: Activity Preceding Activities Completion Times (to, tm, tp) A - 5, 6, 7 B - 4, 5, 6 C B 3, 4, 5 D C

Activity Preceding Activities Completion Times (to, tm, tp)
A - 5, 6, 7
B - 4, 5, 6
C B 3, 4, 5
D C 10, 12, 14
E A, D 5, 6, 7
F C, E 3, 10, 11
G E 4, 5, 6
H G, F 5, 7, 9
  1. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities.
  2. Find the probability of completing the project in 45 weeks.