Question: Activity Preceding activity Activity duration A - 6 B - 3 C - 1 D A, B 2 E A, C 5 F D, E
|
Activity |
Preceding activity | Activity duration |
| A | - | 6 |
| B | - | 3 |
| C | - | 1 |
| D | A, B | 2 |
| E | A, C | 5 |
| F | D, E | 2 |
| G | D, F | 6 |
- Draw an AON diagram based on the activities and their relationships given in the table. (1 mark)
- Find the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF), and Slack time for each activity of the project. (1 mark)
- Determine the slack time for each path. (1 mark)
- Find the critical activities and critical path. (1 mark)
- Determine the length of the project. (1 mark)