Question: Activity Preceding activity Activity duration A - 6 B - 3 C B 1 D A 2 E B, D 5 F C, D 2
| Activity | Preceding activity | Activity duration |
| A | - | 6 |
| B | - | 3 |
| C | B | 1 |
| D | A | 2 |
| E | B, D | 5 |
| F | C, D | 2 |
| G | E, F | 6 |
-
Draw an AON diagram based on the activities and their relationships given in the table.
-
Find the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF), and Slack time for each activity of the project.
-
Determine the slack time for each path.
-
Find the critical activities and critical path.
-
Determine the length of the project.