Question: Activity Preceding Time A -- 8 B -- 4 C B 3 D A 3 E A, C 3 F D, E 4 (3) What
| Activity | Preceding | Time |
| A | -- | 8 |
| B | -- | 4 |
| C | B | 3 |
| D | A | 3 |
| E | A, C | 3 |
| F | D, E | 4 |
(3) What is project completion time?