Question: Activity Preceding Time A -- 8 B -- 4 C B 3 D A 3 E A, C 3 F D, E 4 (5) If

Activity Preceding Time
A -- 8
B -- 4
C B 3
D A 3
E A, C 3
F D, E 4

(5) If activity B is delayed by 1 weeks, will the project be delayed due to that? Why?