Question: Activity Pred. Normal duration (day) Crash duration (day) Normal cost (TL) Crash cost (TL) X - 4 2 100 160 Y X 7 4 100
| Activity | Pred. | Normal duration (day) | Crash duration (day) | Normal cost (TL) | Crash cost (TL) |
| X | - | 4 | 2 | 100 | 160 |
| Y | X | 7 | 4 | 100 | 145 |
| Z | Y | 9 | 8 | 100 | 120 |
| T | Y | 4 | 2 | 100 | 180 |
| W | Y | 3 | 1 | 100 | 140 |
| U | W | 5 | 2 | 100 | 190 |
| V | Z,U | 2 | 1 | 100 | 140 |
a) Write the Linear Programming to be solved to minimize the total cost of completing the project within 19 days.
b) Find the solution with the simplex algorithm (use Excel Solver). Discuss the results.