Question: Given the following project Activity Pred. Normal duration (day) Crash duration (day normal cost ($) crash cost ($) A - 5 3 154 232 B

Given the following project

Activity Pred. Normal duration (day) Crash duration (day normal cost ($) crash cost ($)
A - 5 3 154 232
B - 4 2 82 164
C - 4 2 92 126
D B,C 2 1 64 150
E A,B,C 6 4 120 200
F C 3 1 80 280
G D 4 3 181 218

a) Find the optimal cost. Show the crash analysis on the network step by step. Overhead cost = 100 $/day

b) Draw the cost-duration graphic.