Question: Activity Predecessor a m b Expected time Variance A -- 2 5 8 B A 2 6 7 C D 4 5 7 D A

Activity

Predecessor

a

m

b

Expected time

Variance

A

--

2

5

8

B

A

2

6

7

C

D

4

5

7

D

A

6

12

14

E

D

4

7

13

F

B,C

6

8

16

G

E,F

2

6

7

A project has the following activities, along with their estimate for completion.

a) calculate the expected time and variance for each activity

b) Draw the critical path diagram

c) Show the early start, the early finish times, the late start, and the late finish times

What is the critical path?

A. AG

B. ABFG

C. ADCFG

D. ADEG

E. None of these

What is the variance of the critical path?

A. 4.32

B. 5.75

C. 4.25

D. 6.5

E. None of these

What is the probability that the project can be completed in 34 weeks.

A. .7845

B. 22%

C. 78%

D. 34%

E. None of these

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!