Question: In the following table task durations are given in weeks. Use the information to answer the questions: Activity Predecessor Optimistic Normal Pessimistic Expected Time Variance
In the following table task durations are given in weeks. Use the information to answer the questions:
| Activity | Predecessor | Optimistic | Normal | Pessimistic | Expected Time | Variance |
| A | None | 2 | 4 | 6 |
|
|
| B | None | 3 | 5 | 9 |
|
|
| C | A | 4 | 5 | 7 |
|
|
| D | A | 4 | 6 | 10 |
|
|
| E | B, C | 4 | 5 | 7 |
|
|
| F | D | 3 | 4 | 8 |
|
|
| G | E | 3 | 5 | 8 |
|
|
Calculate the expected time and variance for each task
Draw the network and find the critical path and time
Find the probability that the critical path will be completed in 23 weeks