Question: In the following table task durations are given in weeks. Use the information to answer the questions: Activity Predecessor Optimistic Normal Pessimistic Expected Time Variance

In the following table task durations are given in weeks. Use the information to answer the questions:

Activity

Predecessor

Optimistic

Normal

Pessimistic

Expected Time

Variance

A

None

2

4

6

B

None

3

5

9

C

A

4

5

7

D

A

4

6

10

E

B, C

4

5

7

F

D

3

4

8

G

E

3

5

8

Calculate the expected time and variance for each task

Draw the network and find the critical path and time

Find the probability that the critical path will be completed in 23 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!