Activity Predecessor Activity Optimistic time Most like time Pessimistic time A _ 2 4 6 B A
Fantastic news! We've Found the answer you've been seeking!
Question:
Activity | Predecessor Activity | Optimistic time | Most like time | Pessimistic time |
A | _ | 2 | 4 | 6 |
B | A | 4 | 5 | 6 |
C | A | 7 | 10 | 13 |
D | B, C | 5 | 6 | 7 |
E | C | 3 | 4 | 5 |
F | D | 12 | 15 | 18 |
G | E, F | 8 | 9 | 12 |
Consider the project with the following information above
Draw a network diagram for the project.
Related Book For
Income Tax Fundamentals 2013
ISBN: 9781285586618
31st Edition
Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill
Posted Date: