Question: Barbara Gordon, the project manager for web Ventures, Inc., compiled a table showing time estimate for each of the companys manufacturing activities of a project,
Barbara Gordon, the project manager for web Ventures, Inc., compiled a table showing time estimate for each of the company’s manufacturing activities of a project, including optimistic, most likely and pessimistic,
a. Calculate the expected time, te for each activity.
b. Calculate the variance, Ï2 for each activity
.png)
Activity Optimistic (days) Most Likely (days) Pessimistic (days) 19 18 16 20 12 15
Step by Step Solution
3.56 Rating (180 Votes )
There are 3 Steps involved in it
Web Ventures Inc Activity Statistics Activity Optimistic Most L... View full answer