Question: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 25 31 43 B 1

TIMES (days)

Activity Start Node Finish Node

OPTIMISTIC

to

MOST LIKELY

tm

PESSIMISTIC

tp

A 1 2 25 31 43
B 1 3 24 30 48
C 2 5 18 30 42
D 3 4 29 53 77
E 4 5 13 25 61

Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity A.........te= 32 Standard Deviation = 3 Activity B.........te=

Standard Deviation =

Activity C.........te=

Standard Deviation =

Activity D.........te=

Standard Deviation =

Activity E.........te=

Standard Deviation = 8 Path 1 - 2 - 5 Mean Time =

Standard Deviation =5 Path 1 - 3 - 4 - 5 Mean Time =

Standard Deviation =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!