Question: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 25 31 43 B 1
| TIMES (days) |
| ||||
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 25 | 31 | 43 |
| B | 1 | 3 | 24 | 30 | 48 |
| C | 2 | 5 | 18 | 30 | 42 |
| D | 3 | 4 | 29 | 53 | 77 |
| E | 4 | 5 | 13 | 25 | 61 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity A.........te= 32 Standard Deviation = 3 Activity B.........te=
Standard Deviation =
Activity C.........te=
Standard Deviation =
Activity D.........te=
Standard Deviation =
Activity E.........te=
Standard Deviation = 8 Path 1 - 2 - 5 Mean Time =
Standard Deviation =5 Path 1 - 3 - 4 - 5 Mean Time =
Standard Deviation =