Question: Activity Predecessor Crash cost (slope) Maximum crash time Normal time Normal cost A - 10 1 4 30 B - 70 2 7 60 C

Activity

Predecessor

Crash cost (slope)

Maximum crash time

Normal time

Normal cost

A

-

10

1

4

30

B

-

70

2

7

60

C

A

0

0

1

80

D

B

20

2

4

40

E

B

50

3

5

110

F

C

200

3

5

90

G

D

30

1

2

60

H

E

40

1

2

70

I

F,G,H

0

0

2

140

Consider the following data for a project. Draw the project network. Compute the total direct cost for each project duration. If the indirect costs for each duration are $1,200 for 16 days, $1,130 for 15 days, $1,000 for 14 days, $900 for 13 days, $860 for 12 days, $820 for 11 days and $790 for 10 days, compute the total project cost for each duration. Plot the total direct, indirect, and project costs for each of these durations on a cost-time graph. What is the optimum cost-time schedule for the project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!