Question: Activity Predecessor Crashing Normal Time Time (days) (days) 51 7 B 5 Crashing Cost/day $200 $500 $200 $300 $400 $650 $500 $350 . 10 2

Activity Predecessor Crashing Normal Time Time (days) (days) 51 7 B 5 Crashing Cost/day $200 $500 $200 $300 $400 $650 $500 $350 . 10 2 1 F AC AGB 2 1 1 What is the critical path for this project using the normal times? O A. C-F B. B-E-H OC. B-G-H OD. A-D-H