Question: Activity Predecessor Duration A - 2 B A 3 C A 2 D B 4 E C 3 F C 4 G D, E 5

Activity

Predecessor

Duration

A

-

2

B

A

3

C

A

2

D

B

4

E

C

3

F

C

4

G

D, E

5

H

G, F

4

Draw the network diagram and calculate the forward direction