Question: Study the table below and answer the questions that follow: Activity Predecessor Duration A 4 B A 3 C A 4 D A 5 E
Study the table below and answer the questions that follow:
| Activity | Predecessor | Duration |
| A | 4 | |
| B | A | 3 |
| C | A | 4 |
| D | A | 5 |
| E | B,C | 3 |
| F | E,D | 3 |
| G | F | 4 |
| H | F | 6 |
| I | G,F | 5 |
| J | I,H | 5 |
Draw the network diagram for the activities noted above. (18)
3.2 Calculate the critical path for the activities. (7)