Question: Study the table below and answer the questions that follow: Activity Predecessor Duration A 4 B A 3 C A 4 D A 5 E

Study the table below and answer the questions that follow:

Activity Predecessor Duration
A 4
B A 3
C A 4
D A 5
E B,C 3
F E,D 3
G F 4
H F 6
I G,F 5
J I,H 5

Draw the network diagram for the activities noted above. (18)

3.2 Calculate the critical path for the activities. (7)