Question: ACTIVITY PREDECESSOR DURATION ( DAYS ) A - 1 5 B - 2 5 C A;B 1 0 D B 1 3 E C;D 8

ACTIVITY PREDECESSOR DURATION (DAYS)
A
-
15
B
-
25
C
A;B
10
D
B
13
E
C;D
8
F
A
9
G
E;F
12
4.1 Identify the paths for this network and state the critical path. (5)
4.2 Calculate the Early Start (ES); Early Finish (EF); Late Start (LS) ; Late Finish (LF) and slack for each activity.