Question: ACTIVITY PREDECESSOR DURATION ( DAYS ) A - 1 5 B - 2 5 C A;B 1 0 D B 1 3 E C;D 8
ACTIVITY PREDECESSOR DURATION DAYS
A
B
C
A;B
D
B
E
C;D
F
A
G
E;F
Identify the paths for this network and state the critical path.
Calculate the Early Start ES; Early Finish EF; Late Start LS ; Late Finish LF and slack for each activity.