Question: Activity Predecessor Duration Optimistic Most Likely Pessimistic t e s 2 s Critical (Y/N)? A - 8 14 20 ? ? ? ? B A

Activity Predecessor Duration
Optimistic Most Likely Pessimistic te s2 s Critical (Y/N)?
A - 8 14 20 ? ? ? ?
B A 3 12 21 ? ? ? ?
C B 8 11 14 ? ? ? ?
D B 6 6 6 ? ? ? ?
E B 8 14 20 ? ? ? ?
F C, D 8 11 14 ? ? ? ?
G D 4 10 25 ? ? ? ?
H E, G 4 10 16 ? ? ? ?

Part 1 - Complete the table by calculating the expected time, variance and standard deviation for every task. . Replace the "?" with your values.

Place a "Y" in the last column, if the activity is critical.

Place a "N" in the last column, if the activity is non-critical.

Part 2:

2.1. Expected Completion of this project is
2.2. Probability of finishing this project 10 days sooner is?
2.3 What is the target date with 75% probability of being met?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!