Question: Activity Predecessor Duration Optimistic Most Likely Pessimistic t e s 2 s Critical (Y/N)? A - 8 14 20 ? ? ? ? B A
| Activity | Predecessor | Duration | ||||||
| Optimistic | Most Likely | Pessimistic | te | s2 | s | Critical (Y/N)? | ||
| A | - | 8 | 14 | 20 | ? | ? | ? | ? |
| B | A | 3 | 12 | 21 | ? | ? | ? | ? |
| C | B | 8 | 11 | 14 | ? | ? | ? | ? |
| D | B | 6 | 6 | 6 | ? | ? | ? | ? |
| E | B | 8 | 14 | 20 | ? | ? | ? | ? |
| F | C, D | 8 | 11 | 14 | ? | ? | ? | ? |
| G | D | 4 | 10 | 25 | ? | ? | ? | ? |
| H | E, G | 4 | 10 | 16 | ? | ? | ? | ? |
Part 1 - Complete the table by calculating the expected time, variance and standard deviation for every task. . Replace the "?" with your values.
Place a "Y" in the last column, if the activity is critical.
Place a "N" in the last column, if the activity is non-critical.
Part 2:
| 2.1. Expected Completion of this project is | ||||
| 2.2. Probability of finishing this project 10 days sooner is? | ||||
| 2.3 What is the target date with 75% probability of being met? | ||||