Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost per day Max Crash Time A None 5 $ 5 0 3 $

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost per day Max Crash Time
A None 5 $503 $1502
B None 44022002
C b 77061601
D a,c 2201501
E a,c 330 NA NA NA
F b 88052903
G d 55041001
H e,f 66031803