Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost/day Max Crash A - 5 $500 3 $1,500 ? Part A: Fill in
Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost/day Max Crash A - 5 $500 3 $1,500 ? Part A: Fill in the values for Crash cost/day B - 4 $400 2 $2,000 ? C B 7 $700 6 $1,600 ? Note: You don't need to submit the network diagram, but it is strongly recommended the you make a network diagram that you will use as you decide how many paths you have, their length, and then use the network as you crash activities. Scroll down to see parts D, E, and F. D A, C 2 $200 1 $500 ? E A, C 3 $300 - - - F B 8 $800 5 $2,900 ? G D 5 $500 4 $1,000 ? H E, F 6 $600 3 $1,800 ? Part A
Path Duration (Normal Time) Direct Cost Indirect Cost Total Cost ? Part C replace the "?" with the Total cost of the project. Assume an indirect cost of $250/day Part D: Compress the schedule by crashing twice - Each crash should reduce the completion time by 1 day. Path 1st Crash 2nd Crash
Activity(ies) Crashed Crash Cost Direct Cost Indirect Cost Total Cost Part E: Compress the schedule by TWO more days. Each crash should reduce the completion time by 1 day. Show your work in the table. Path 3rd Crash 4th Crash Activity(ies) Crashed Crash Cost Direct Cost Indirect Cost Total Cost Part F: Compress the schedule to the shortest possible time for this project. Each crash should reduce the completion time by 1 day. Show your work in the table. (there maybe more columns/rows than needed) Path 5th Crash 6th Crash 7th Crash 8th Crash
Activity(ies) Crashed Crash Cost Direct Cost Indirect Cost Total Cost
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
