Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost/day Max Crash A - 5 $500 3 $1,500 ? Part A: Fill in

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost/day Max Crash
A - 5 $500 3 $1,500 ? Part A: Fill in the values for Crash cost/day
B - 4 $400 2 $2,000 ?
C B 7 $700 6 $1,600 ? Note: You don't need to submit the network diagram, but it is strongly recommended the you make a network diagram that you will use as you decide how many paths you have, their length, and then use the network as you crash activities. Scroll down to see parts D, E, and F.
D A, C 2 $200 1 $500 ?
E A, C 3 $300 - - -
F B 8 $800 5 $2,900 ?
G D 5 $500 4 $1,000 ?
H E, F 6 $600 3 $1,800 ?
Part A
Path Duration (Normal Time)
Direct Cost
Indirect Cost
Total Cost ? Part C replace the "?" with the Total cost of the project. Assume an indirect cost of $250/day
Part D: Compress the schedule by crashing twice - Each crash should reduce the completion time by 1 day.
Path 1st Crash 2nd Crash
Activity(ies) Crashed
Crash Cost
Direct Cost
Indirect Cost
Total Cost
Part E: Compress the schedule by TWO more days. Each crash should reduce the completion time by 1 day. Show your work in the table.
Path 3rd Crash 4th Crash
Activity(ies) Crashed
Crash Cost
Direct Cost
Indirect Cost
Total Cost
Part F: Compress the schedule to the shortest possible time for this project. Each crash should reduce the completion time by 1 day. Show your work in the table. (there maybe more columns/rows than needed)
Path 5th Crash 6th Crash 7th Crash 8th Crash
Activity(ies) Crashed
Crash Cost
Direct Cost
Indirect Cost
Total Cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!