Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash Cost Per Day A - 1 2 2 0 0 9 3 5 0

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash Cost Per Day
A -12200935050
B A 830063000
C A 92507450100
D B 64005600200
E B,C 5150422575
F C 105009650150
G D,E,F 84006900250