Question: Activity Predecessor Normal Time(weeks) Crash time(weeks) Normal cost($) Crash Cost($) A --- 3 1 1500 2500 B A 4 2 2000 2500 C B 5
| Activity | Predecessor | Normal Time(weeks) | Crash time(weeks) | Normal cost($) | Crash Cost($) |
| A | --- | 3 | 1 | 1500 | 2500 |
| B | A | 4 | 2 | 2000 | 2500 |
| C | B | 5 | 3 | 2500 | 3500 |
| D | A | 4 | 2 | 2000 | 2750 |
| E | D | 4 | --- | 2750 | --- |
| F | A | 6 | 4 | 3000 | 4000 |
| G | C,E,F | 8 | 6 | 5000 | 7500 |
1. Determine the project completion time? *
a. 20 weeks
b. None
c. 22 weeks
d. 21 weeks
2. Determine the projects critical path? *
a. AFG
b. ABCG
c. NONE
d. ADEG
3. Calculate the cost of crashing activity of B? *
a. 375
b. None
c. 500
d. 250
4. Calculate the activities crashing cost of E? *
a. 375
b. None
c. 500
d. 0
5. To Crash the project by one-time unit, which activity would you start with? *
a. B
b. A
c. C
d. None
6. The number of crashing of the activity chosen in number 5 is: *
a. 3
b. 2
c. None
d. 1
7. To Crash the project by another time unit, which activity would you take? *
a. None
b. A
c. B & E
d. B & D
8. Determine the cost of the activity that is crashed in part 7? *
a. 500
b. 100
c. 375
d. None
9. To crash the project by another more week activity which activity must be crashed: *
a. B & E
b. A
c. C & D
d. None
10. The total crashing cost so far after crashing the above activities is: *
a. $1500
b. $500
c. None
d. $1250