Question: Activity Predecessor Optimistic Most Likely Pessimistic A 4 7 10 B 2 9 10 C A,B 2 5 8 D C 16 19 28 E

Activity Predecessor Optimistic Most Likely Pessimistic
A 4 7 10
B 2 9 10
C A,B 2 5 8
D C 16 19 28
E C 6 9 24
F E 1 7 13
G C 4 10 28
H D,F 2 5 14
I G,F 5 8 17
J H,I 2 5 8
  1. Determine the expected completion time for each activity.
  2. Construct the AON network for the activities of this contract and determine the critical path for the project.