Question: Question 2. What is the probability that the project will be completed within 100 days? Activity Predecessor optimistic most likely pessimistic A - 8 10

Question 2. What is the probability that the project will be completed within 100 days? Activity Predecessor optimistic most likely pessimistic A - 8 10 14 B - 14 20 26 C A, B 16 20 22 D A, B 24 30 36 E C 28 36 46 F D, E 18.5 20 21.5